_________年_________月_________日_________(简称甲方)_________(简称乙方)签订安装_________项目合
1.安装工程名称:_________
2.工程点:甲方_________港口
3.工程范围:合附图纸估价单
4.完工期限:安装工程配合甲方_________甲方港口建造工程完工_________天完成安装工程中包括_________试验运行
5.安装工程总价格:_________美元整
6.安装工程付款进度:
第期:甲方合开始实施时付乙方工程总价15_________美元整
第二期:甲方_________港口造船工程开始时付乙方工程总价15_________美元整
第三期:安装路时甲方付乙方工程总价10_________美元整
第四期:机设备运抵工时甲方付乙方工程总价40_________美元整
第五期:安装工程完毕时甲方付乙方工程总价10_________美元整
第六期:工程验收合格甲方付乙方工程总价余额10_________美元整
7.违约罚款:乙方原未准时完工时应乙方负责应付违约罚款天总价1计算_________美元整
8.增加减少工程:甲方需修改增加减少工程计划时总价增减应双方规定订单计算需新增加工程量双方应行协商该项新增加工程单价甲方修改原计划已完工部分工程已运抵工材料弃置甲方验收应双方规定单价乙方已完成工程费材料费予支付
9.监督进度:甲方派监督员代表工程进度予监督权予监工指导乙方应甲方员代表指示正确施工口置理
10.工程停工:甲方通知乙方工程停止原非乙方责乙方停止工程求甲方已完成工程数量运抵工材料合理费已交款中增付扣
11.工程监护:工程开始完工移交前已完工工程留工材料工具设备等均乙方保力抵抗灾害外乙方应保中切负损害全责遇抵抗天灾祸乙方应详列损害实情甲方提出恢复原状价格日期供甲方核付款甲方决定继续施工合第10条规定结束
12.工程保险:天灾甲方原外乙方应甲方验收保证工程质量良_________年
13.附加条款:工程进行中乙方错甲方员受伤害乙方应负责赔偿果伤害原甲方甲方订约工程员错造成应甲方完全负责
14.附件:合附件应视合部分条款等效力
附件包括:(1)图样(2)估价单
15.合形式:合式两份甲乙双方执份保留两份副供双方存档备查
16.附加条款:机保养——乙方应甲方验收提供免费定期_________保养服务年_________月派员次维护正常运行
合双方签日期生效
甲方(盖章):_________ 乙方(盖章):_________
法定代表(签字):_________ 法定代表(签字):_________
_________年____月____日 _________年____月____日
签订点:_________ 签订点:_________
附件
this contract for project of installing main engine is made on_________ by and between _________ company ltd (here inafter called party a) and _________ company ltd (hereinaftercalled party b)
1 name of installation work _________
2 location of installation work party a's_________in port a
3 scope of installation work as specified in the drawingsand statement attached
4 time limit for completion
the installation work shall cordinate with the construction of _________ in party a and shall be completed including thetrial run for _________ within _________days after the completion of _________
5 total price of installation work_________us d only
6 payment terms of installation work
first installment
party a shall pay to party b fifteen percent of the total pricefor installation work ie_________usd only when thiscontract comes into effect
second installment
party a shall pay to party b fifteen percent of the total pricefor instalatiorn work ie_________u s d only at the commencement of construction installation
third installment
party a shall pay to party b ten percent of the total pricefor installation work ie_________u s d only duringthe installation of pipes
fourth installment
party a shall pay to party b forty percent of the total pricefor installation work ie_________u s d only at thetime when the main equipment arrives at the site
fifth installment
party a shall pay to party b ten percent of the total pricefor installation worki e_________u s d only upon comple tion of the installation work
sixth installment
party a shall pay to party b ten percent of the difference of the price for installation work ie_________u s d only after the work received has been proved qualified
7 penalty for default
in the event party b shall fail to complete the work in timeowing to reasons that party b shall be held liable party b shallpay a penahy for such defauh based on one out of a thousand of the total price for installation work per day ie_________usd only for each day of such default
8 increase or decrease of work
in case party a has to amendincrease or decrease the working schedule the corresponding increase or decrease of total priceshall be evaluated according to the terms and conditions betweenthe two parties should the work be increased the parties shallenter into an agreement for the unit price of additional items should any part of the completed work of any part of the materi als transported to the site have to be abandoned owing to amend ment made by party a party a shall after having received thework pay for each completed work or materials abandoned as perthe unit price specified to party b
9 supervision for progress
the supervision personnel appointed by party a and its rep resentative shall have the authority to supervise the progress or'work and give instruction party b shall perform correctly in ac cordance with such instruction given by party a's personnel orrepresentative
10 stopage work
should party a notify party b to stop the work for reasonsbeyond the responsibility of party b party b can stop the workand claim from party a the price of finished work materials atsite and other reasonable expenses to be added or deducted fromthe paid installments
11 custody of work
the completed work and the materials tools and equipment at site shall be under the custody of party b after commencement and before completion and delivery of the work unless in the event of force majeure party b shall be fully responsible for any damage of the work under the custody of party b in case of force majeure party b shall give a list of damage according to the actual condition and suggest an expected price and date forrecovery from such damage to party a for checking and paymentshould party a decide not to continue with the work thiscontract shall be terminated according to article 10 hereof
12 warranty for work
party b shall warrant the promised condition of the work within _________ year(s) after the date of receiving the work by party a however party b shall not be liable to acts of god or misuse of the work by party a
13 supplemental provisions
party b shall be held responsible if party a's personnel or other people is injured due to the negligence of party b duringthe progress of construction however such responsibility shallrest upon party a if the injury caused is due to the negligence of party a of technicians contracted with party a
14 attachments
attachments shall become an integral part of this contractand shall be as effective as any other provisions attachments include (1) drawings (2) an estimate of cost
15 format of this contract
the contract shall be in duplicate with two texts to be heldseparately by the parties hereof each of the parties shall alsokeep two copies of the contract for record
16 additional provision
maintenace of main engine
party b shall provide free periodic maintenance service forthe main engine of _________ for _________ year(s) after the receiving of the work by party a and send maintenance personnel every _________month(s) for performing maintenance
this contract has been executed by the parties as of the day and year first above written
party a_________ party b_________
by_________ by_________
address_________ address_________
date_________ date_________
文档香网(httpswwwxiangdangnet)户传