Sample Professional Responsibility exam questions

1  While working on an external project your customer asks you to perform some additional tasks that are not included in the formal contract You should
a Honor the customer's request as sign of cooperation to ensure future business
b Refuse the request and report the customer to your sponsor
c Acknowledge the request and advise the customer to submit a formal change request
d Convene a meeting of the project team and rewrite the scope statement
2 You are managing an internal R&D project The initial test results are very poor You are afraid your management might cancel the project and this could reflect poorly upon you Verification testing could be done quickly and inexpensively You should
a Be the first to recommend canceling the project
b Inform management about the results and wait for a response
c Inform management immediately and recommend retesting for verification
d Withhold the information from management until you perform additional tests to verify the initial results
3 During an informal meeting with your project client you are offered a substantial monetary incentive to alter the configuration of the product to meet the client's personal need This change may result in additional project costs and schedule delays The appropriate action to take would be
a Refrain from accepting the offer and advise the customer to submit a request to the change control board
b Accept the offer and issue an internal configuration change request to the design group
c Obtain additional information about the request and the customer's personal need before accepting the offer
d Delay acceptance of the offer until you can ensure that you can protect yourself from any legal liabilities
4 As the project manager for a very large and highly visible project you receive a preliminary press release for your approval before distribution You are expected to approve the release without comment Your review identifies a major discrepancy regarding some key project financial estimates that may mislead the intended recipients As the project manager it is your responsibility to
a Inform the project sponsor of the discrepancy and refuse to approve the release
b Approve the release but send a memo to the sponsor advising that you are aware of the discrepancy and will refer any questions your receive to the sponsor
c Completely rewrite the press release and include the correct information
d Approve the release as requested
5 Your project is running out of cash and significant work remains You are directed by senior management to instruct your people to use another project's charge numbers while working on your project You should
a Follow instructions
b Inform the corporate auditors
c Understand the background of management's instructions before taking any action
d Shut down the project if possible
6 While reviewing the estimates from the functional managers assigned to your project you discover that one cost estimate is clearly higher than those submitted for previous projects You should
a Reject the estimate and remove the functional manager from the project
b Request the supporting details for the estimate to ensure it has been properly prepared
c Accept the estimate and plan to use the additional funding as a reserve
d Question each functional manager for information about this estimate
7 You are working in a country where it is customary to exchange gifts between contractor and customer Your company code of conduct clearly states that you cannot accept gifts from any client Failure to accept the gift from this client may result in termination of the contract The action to take in this case would be
a Provide the customer with a copy of your company code of conduct and refuse the gifts
b Exchange gifts with the customer and keep the exchange confidential
c Contact your project sponsor and or your legal or public relations group for assistance
d Ask the project sponsor or project executive to exchange gifts
8 During your assignment as project manager you add a new member to your project team This new team member was recently hired from a competitor and offers to share a substantial amount of proprietary information from his previous company This information could put you and your team in a very strong position for future business You are aware of a non compete clause in the new hire's condition of employment You should
a Accept the information and agree to keep it confidential between you and the new hire
b Review the condition of employment with the new hire and advise her to reconsider the offer
c Review the information and only accept only what may have a direct impact on the project's financial status
d Ignore the offer to share and move forward with the project
9 You are asked to write a paper for your sponsor so that heshe can present it at a technical meeting You are informed that hisher name will be the only name on the paper You should
a Follow instructions
b Follow instructions but demand that your name also appears
c Refuse to follow the instructions
d Go over the head of your sponsor seeking advice
10 An example of a conflict of interest would be
a As a public official you make a decision about a contract award that will benefit you personally
b You and a functional manager disagree with a task cost estimate
c Your sponsor decides to cancel your project because it no longer supports the company strategy
d Your personality conflicts with that of a key member of your project team
11 Each of the following describes the use of an ethical approach except
a Attempting to understand the religious and cultural sensitivities of the country in which you have been assigned
b Ensuring that personal interest does not interfere with your decision making process
c Accepting gifts in exchange for favoring one contractor over another
d Maintaining confidentiality of sensitive information obtained during the project life cycle
12 To maintain the customer's schedule massive overtime will be required between Christmas and New Years Many of your team members have put in for vacation during this time You should
a Let the schedule slip and inform the customer
b First give the employees the choice of working overtime
c Make the employees cancel their vacation plans and work overtime
d Hire temporary employees for the overtime
13 Which of the following situations describes a violation of the PMPProfessional Code of Conduct
a Accepting a gift that is within the customary guidelines of the country or province you are currently working in
b Use of confidential information to advance your position or influence a critical decision
c Complying with laws and regulations of the state or province in which project management services are provided
d Disclosing information to a customer about a situation that may have an appearance of impropriety
14 In order to balance the needs of the many stakeholders involved in your project the most desirable method to achieve resolution of conflicts would be
a Compromise
b Forcing
c Controlling
d Confrontation
15 You receive a contract to perform testing for an external client After contract award the customer provides you with the test matrix to use for your 16 tests The vice president for engineering says that the customer's test matrix is wrong and she will use a different test matrix which should give better results This is a violation to the SOW Suppose your sponsor is also the vice president for engineering You should
a Use the customer's test matrix
b Use the engineering test matrix without telling the customer
c Use the engineering test matrix and inform the customer
d Tell your sponsor that you want to set up a meeting with the customer to resolve the conflict
16 In order for the project manager to fully and effectively understand a stake holder's personal concerns or grievances it may necessary to
a Ask for a written description of the problem and submit it through the project office
b Schedule a project review session with the entire project team
c Attempt to empathize with the stakeholder
d Involve the project sponsor as an arbitrator
17 As the leader of a project team the project manager may be required to assess the competencies of his or her team members Occasionally some weaknesses or areas for improvement will be identified The project manager should
a Remove any team members who have demonstrated weaknesses in critical knowledge areas
b Communicate those weaknesses and establish a performance improvement program
c Hire additional resources to compensate for weak areas
d Wait for the team members to fail in an assignment to justify termination
18 You have just changed jobs and discovered that your new employer routinely violates OSHAEPA and affirmative action requirements on projects You should
a Do nothing it's not your problem
b Start by asking management if they are aware that regulations are being violated
c Talk to the corporate legal department
d Inform the appropriate government agencies about the violations
19 The project manager must be an effective communicator to ensure that project stakeholders receive and understand project related information and status Prior to delivering information to the stakeholders the project manager should attempt to
a Research and understand the region of experience of the stakeholder before transmitting information
b Identify only those stakeholders that have a the same background experience as the project manager
c Filter the information to remove any details
d Restrict information to specific technical details
20 As part of your project plan you must develop an effective method of communication for your multinational team of stakeholders You have several choices of media available The appropriate action to take in the development of the communication plans would be to
a Discuss the available options with the stakeholders and obtain their input
b Use the standard media that has been in effect for your previous projects
c Use multiple forms of media to ensure that everyone receives the information
d Obtain additional funding from the project sponsor and develop a project specific communications infrastructure
21 One of your employees is up for promotion If the promotion is granted the employee will be reassigned elsewhere causing a problem for you on your project You can delay the promotion until your project is completed You should
a Support the promotion but work with the employee and the employee's new management to develop a good transition plan
b Ask the employee to refuse the promotion until your project is completed
c Arrange to delay the promotion until the project is completed
d Tell the employee that it is his responsibility to find a suitable replacement so that the project will not suffer
22 The integrity of the project manager is often challenged by stakeholders who attempt to use personal power or influence to change the scope of an agreed upon deliverable In these situations the project manager's most appropriate response would be
a Refer the stakeholder to the process for change documented in the approved contract
b Agree to the change because customer satisfaction is the goal regardless of cost
c Contact the legal department and suspend all further project work
d Determine the risks and rewards for implementing the change before taking any action
23 During project implementation the client interprets a clause in the contract to mean the he is entitled to a substantial refund for work recently completed You review the clause and disagree with the client's conclusion As the project manager which of the following actions should be taken
a Disregard the customer's conclusion and continue to process invoices
b Document the dispute and refer to the provisions of the contract that address interpretations and disputes
c Advise the customer that ambiguous information in contracts is always interpreted in favor of the contractor
d Immediately correct the clause to remove any possible misinterpretation by the customer
24 Your executives in appreciation for the success of your project have given you a 10000 bonus to be disbursed among your fiveteam members One of the five who is a substandard worker and accomplished very little on your project is in your car pool You should
a Provide everyone with an equal share
b Provide everyone a share based upon their performance
c Ask the workers to decide among themselves how the bonus should be subdivided
d Ask the sponsor to make the decision
25 Before reporting a perceived violation of an established rule or policy the project manager should
a Determine the risks associated with the violation
b Ensure there is a reasonably clear and factual basis for reporting the violation
c Ignore the violation until it actually affects the project results
d Convene a committee to review the violation and determine the appropriate response
26 Project Managers can contribute to their organization's knowledge base and to the profession of project management most effectively by
a Developing and implementing a project review and lessons learned process
b Establishing strict guidelines for protecting intellectual property
c Promote the use of ad hoc project management
d Ensuring that all project plans are developed before the project team is formed
27 You have been assigned two concurrent projects Because of the nature of the projects you have a conflict of interest You should
a Do the best you can and tell no one
b Ask to be removed from one of the projects
c Ask to be removed from both of the projects
d Inform your sponsor and ask for his advice
28 You receive a contract to perform testing for an external client After contract award the customer provides you with the test matrix to use for your 16 tests The vice president for engineering says that the customer's test matrix is wrong and she will use a different test matrix which should give better results This is a violation to the SOW You should
a Use the customer's test matrix
b Use the engineering test matrix without telling the customer
c Use the engineering test matrix and discuss the reasons with the customer
d Ask your sponsor for clarification assuming that the vice president is not your sponsor
29 An effective method for improving an organization's project management knowledge base is through
a Coaching and mentoring
b Referent power
c A weak Matrix organizational structure
d Fast Tracking

Answer Key
1c
8b
15d
22a
2d
9b
16c
23b
3a
10a
17b
24c
4a
11c
18b
25b
5c
12b
19a
26a
6b
13b
20a
27d
7c
14d
21a
28d



29a


文档香网(httpswwwxiangdangnet)户传

《香当网》用户分享的内容,不代表《香当网》观点或立场,请自行判断内容的真实性和可靠性!
该内容是文档的文本内容,更好的格式请下载文档

下载文档,方便阅读与编辑

文档的实际排版效果,会与网站的显示效果略有不同!!

需要 2 积分 [ 获取积分 ]

购买文档

相关文档

PMP考试模拟题(28个)

Sample Professional Responsibility exam questions1.  While working on an external project your customer asks you to perform some additional tasks that are not included in the formal contract. You

h***9 10年前 上传593   0

PMP考试学习心得

PMP考试学习心得  我几乎都是利用自己的业余时间进行PMP和项目管理学习的,一般都在项目上很忙,时间时非常的宝贵的,我最初就是这样计划的,一定找一家让我省力气的、高效的培训班,这样我投入的精力也会少些,所以在选机构上花了大把时间考察。后来证明,这个过程的确是磨刀不误砍柴工,我筛选了几家培训机构之后,选了智鼎东方。  我把备考PMP就定义成一个项目,用项目管理的办法管理学习,整个备考过程

L***9 12年前 上传426   0

PMP考试的100个关键点

1. 一个项目在启动阶段会进行量级估算,准确范围是-50至100%。2000版的量级估算准确度为:-25%到+75%。 参考:PMBOK2004 P161 CH P137 7.1 成本估算。 2. 质量控制通常先于范围确认执行,但这两个过程可以并列进行参考3. Cost-plus-fixed-fee(CPFF) 成本加固定费用合同。成本补偿型合同包括成本加固定费用(CPFF)、成本加

i***i 12年前 上传459   0

2002年PMP考试的一些信息

          2002年PMP考试的一些信息一、2002年PMP考试日期表考试日期3月23日6月22日9月21日12月7日报名截止日期1月15日4月12日7月12日9月30日提交材料截止日期1月18日4月18日7月18日10月4日退考截止日期2月15日5月13日8月2日10月30日缓考截止日期

z***2 14年前 上传455   0

PMP考试模拟试题(40题)

考前模拟试题 Disclaimer: These questions are intended for study purposes only. Success on these questions is not indicative of success on the Project Management Professional Certification Examination. T

h***9 12年前 上传642   0

PMP考试技巧24计

PMP考试技巧24计 第1计 先调查,后决策例1:在新公司,你发现公司的一些财物报告没有遵照会计准则,所以并不准确,在这种情况下,你首先要做的是? A、将公司不准确的记账操作通知政府B、与你的财物经理沟通,告知他你为什么认为他们违反了会计准则C、既然你是公司的新员工,你假设公司的财务标准是不同的,所以不用采取任何行动D、与你以前的财务经理交流,对新公司的会计标准获得专家

j***8 9年前 上传451   0

PMP项目管理模拟考试卷——17-成都模拟题

1. To help the project team function more efficiently on complex and interrelated tasks, the project manager decides to use a war room. What does this mean?A. All the project records are kept in ma

y***l 12年前 上传438   0

PMP项目管理模拟考试卷——18-成都模拟题答案

模拟题答案1C21C41D61C81C2C22D42D62B82A3B23D43B63A83A4A24B44D64A84B5A25B45C65C85B6B26A46A

y***i 10年前 上传600   0

pmp学习心得

pmp学习心得第一篇:pmp学习心得pmp考试心得三个月紧张而富挑战的pmp备考结束了, pmp考试也是一个理顺项目管理思路的过程,在知识点,尤其是职业道德的理解上要以pmp思路对待,重要的是理解pmi的概念和思想。同时也将如何进行项目管理的水平又提升到一个新的高度,发现了诸多平时工作中存在的问题,也对今后起到了指导与改正的作用,真正是受益匪浅。1. 学到的知识总结pmbok

w***i 10年前 上传508   0

PMP学习心得

PMP学习心得  我参加的XX年1月的培训班,3月23日考试。成绩不算高但庆幸通过了,回顾整个学习,复习,考试各阶段,把自己的经验教训总结分享给各位同学。  01. 提前报名,课前通读一遍。    坦白说,我是属于笨鸟先飞的类型,12月中旬开始看pmbok,从第五章开始看,依据恒佳提供的打印版复习题为线索,根据问题在pmbok中找答案,把每章的问题都看一遍,在书中找一遍答案,基本pm

姜***8 10年前 上传600   0

PMP项目管理模拟考试卷——5-科兹纳PMP模拟试卷

概述1、项目是一系列——的活动和任务。A、具有特定目标。B、具有明确开始和终止日期。C、资金有限(如果可用)。D、消耗资源。E、以上皆是。2、成功的项目管理可以被定义为——达到了项目管理目标。A、及时地。B、没有成本超支。C、在设计的性能/技术水平上。D、以上皆是。 E、只有A和B。3、项目管理的好处在于能够——辨别问题,从而产生——。

y***2 12年前 上传969   0

PMP道德规范

PMI MEMBER ETHICAL STANDARDSMEMBER CODE OF ETHICS The Project Management Institute (PMI) is a professional organization dedicated to the development and promotion of the field of project ma

y***x 9年前 上传463   0

一次性成功通过PMP考试的备考经验交流

一次性成功通过PMP考试的备考经验交流  一、选择学习的方式  在短暂紧张的应考时间里,如何顺利通过PMP的考试?这就要在考试前做好充分的考前时间安排,做好应试的学习与复习计划。最好的应试策略就是组成一个学习小组,我们称之为应试项目小组。这样可以保障最佳的学习效果,同时也最大程度上避免了纯记忆形的学习方法,使得小组成员在学习和交流讨论的过程中得到最佳的理解,项目知识的学习最为扎实。成为应

娟***子 11年前 上传445   0

PMP应试六步法

1、 我们既然决定要去考 PMP,那就要做一些前期准备工作了,我自己事先在网上看一些关于 PMP 的一些资料,当然这些都是先了解一下,比如:什么是 PMI 协会、有关 PMP考试的相关信息、PMP 考试报名的相关条件、PMP 培训的机构等等,初步了解之后,就尽量早报名,这样可以早拿到资料和老师的提供的学习计划,这样可根据这些资料和老师的计划安排好自己的计划;  2、那么,接下来我来谈谈如

h***j 10年前 上传661   0

PMP Preparation Overview Updated for PMBOK 2000

PM AreaArea ProcessImportant Tools and TechniquesMajor Deliverables (Outputs)Process GroupOther NotesProject Integration Management – Processes required to ensure that the various element

f***e 14年前 上传618   0

PMP和PRINCE2的价值所在

PMP和PRINCE2的价值所在  我是项目管理专职讲师,很多学员朋友会问我同样的问题:“PMP和PRINCE2到底有什么区别?哪个含金量更高?”看来,这是所有要参加认证的朋友普遍关心的问题,我将根据自己的切身体会,从三个方面回答这个问题,希望共同探讨,对学员朋友带来帮助。  一、认证情况  1、PMP(项目管理专业人士资格认证)是PMI(美国项目管理协会)最有影响力的产品,PMBO

h***6 12年前 上传525   0

PMP培训学习心得

PMP培训学习心得  section 1学习篇  pmp考试不是你背书有多厉害就能通过,而是重在理解。考试能获得越多的p,说明你对项目管理的理解就越接近pmi的思维理念。  两个月时间内,平均每天花3个小时看书,按照老徐的讲义和辅导书,结合自己的学习方法进行学习。  (1)计划。  学习一定得有计划,尤其是要在两三个月时间内学习pmp这样的新体系,我们更应该把pmp考试作为一

j***n 10年前 上传497   0

PMP项目管理模拟考试卷——22-IPMA C级试卷

华鼎项目管理论坛 国际项目管理专业资质认证(IPMP) 知识考核笔试试题 级 别: IPMA C级 应试人员: 准考证号: 分 数: 阅 卷 人: IPMA国际项目管理专业资质认证中国认证委员会 试题1:(20分) 黄河机械公司是一家以

绿***踪 12年前 上传687   0

PMP项目管理模拟考试卷——23-IPMA D级试卷

华鼎项目管理论坛 国际项目管理专业资质认证(IPMP) 知识考核笔试试题 级 别: IPMA D级 应试人员: 准考证号: 分 数: 阅 卷 人: IPMA国际项目管理专业资质认证中国认证委员会 一、判断题 (每小题1分,共20分) 1.

d***3 12年前 上传1018   0

PMP项目管理模拟考试卷——16-2004.模拟考试试题

1. What are the 4 stages of team development?a. Assignment, kick-of, training, communicatingb. Forming, storming, norming, performing c. Direction, motivation, cooperation, collaboration d.

H***1 10年前 上传555   0

PMP学习笔记-沟通管理

PMP学习笔记-沟通管理沟通管理沟通是为了及时与恰当的生成、搜集、传播、存储、检索和最终处置项目信息所需的过程。它在人员与信息之间提供取得成功所必须的关键联系。PM需要花大量时间(75%-90%)与团队、客户、STAKEHOLDER和SPONSOR进行沟通。沟通是一个双向的过程。四个典型过程:沟通规划——确定STAKEHOLDER对信息与沟通的需求。信息发布——将所需信息及时提供给项目STA

d***l 10年前 上传462   0

PMP考生关心的8大问题

1、选择题考试的可靠性如何? PMP选择题考试的可靠性很高!有些人认为四选一的选择题考试不可靠,这是对PMP考试的一个极大误解!随便弄出来的选择题考试,固然不怎么可靠。但,PMP考试的选择题是通过严格的科学研究过程开发出来的,所有题目都要经过从实验环境(相当于自然科学研究中的实验室)到真实考试环境的多种检测,所以PMP考试的题目具有足够的科学性和可靠性。2、PMP考试难不难?

d***s 11年前 上传554   0

您该选择PRINCE2或PMP认证

您该选择PRINCE2或PMP认证  您该选择PRINCE2 或 PMP认证?  很多人都问我,这是一个非常常见的问题,作为一个项目经理,他们是否应选择PRINCE2或PMP认证,因为这两个认证都是全世界非常流行的。  PRINCE2 是一个主要的全球化项目管理流程及方法,PMBOK 则基于框架与项目经理的技巧。它们两个采用不同的方法,但两者的目标都是提高项目执行或成功率。太多的项目

h***2 9年前 上传564   0

PMP(项目管理资格认证)介绍

 PMP(项目管理资格认证)介绍 PMP(Project Management Professional)指项目管理专业人士(人事)资格认证。美国项目管理协会(PMI)举办的项目管理专业人员(PMP)认证考试在全球190多个国家和地区推广,是目前项目管理领域含金量最高的认证。获取PMP证书,不仅提升项目经理的项目管理水平,也直接体现项目经理的个人竞争力,是项目管理专业人士身份的象征。

文***文 10年前 上传631   0

pmp培训心得体会

pmp培训心得体会第一篇:pmp培训心得(一)pmp培训心得(一)一、 考pmp的原因我从事软件开发和管理工作已经十七年了。自从大学毕业以后,对于管理方面的知识我并没有进行过系统的学习。2014年,我曾在上海交大旁听过项目管理专业工程硕士的课程,发现对此很感兴趣,还买了pmbok(第三版)进行自学。但之后的工作中,由于所供职的企业并不是很重视项目管理,所以我的项目管理知识也只限于

n***y 12年前 上传778   0