PMP考试模拟试题(40题)

h***9

贡献于2012-04-18

字数:8587

考前模拟试题
Disclaimer These questions are intended for study purposes only Success on these questions is not indicative of success on the Project Management Professional Certification Examination This download of the Sample Exam Questions is for your personal use and NOT FOR commercial use Any unauthorized use or duplication of this document is prohibited
1 A narrative description of products or services to be supplied under contract is called
a The project plan
B A statement of work
C An exception report
D A Pareto analysis

2 An example of scope verification is
a Reviewing the performance of an installed software module
B Managing changes to the project schedule
C Decomposing the WBS to a work package level
D Performing a benefitcost analysis to determine if we should proceed with the pro

3 Which of the following is not an example of a source of scope change
A A variation in government regulations
B Failure to include a required feature in the design of a telecommunication system
C A need to engage in bottomup cost estimating
D Introducing technology that was not available when scope was originally defined

4 The subdivision of major project deliverables as identified in the scope statement into smaller more manageable components is called
a Parametric estimation
B Scope definition
C Feasibility analysis
D Benefitcost analysis

5 The process of establishing clear and achievable objectives measuring their achievement and adjusting performance in accordance with the results of the measurement is called
a Strategic planning
B Alternative objectives inventory
C Management by objectives
D Contingency planning

6 Configuration management is
a Used to ensure that the description of the project product is correct and complete
B The creation of the work breakdown structure
C The set of procedures developed to assure that project design criteria are met
D A mechanism to track budget and schedule variances

7 A fundamental tenet of modern quality management holds that quality is most likely to be achieved by
a Planning it into the project
B Developing careful mechanisms to inspect for quality
C Striving to do the best job possible
D Conducting quality circle activities

8 Your most recent project status report contains the following information BCWP 3000 ACWP 3500 and BCWS 4000 The schedule variance is
a + 1000
B + 500
C 500
D 1000

9 Learning curve theory emphasizes that in producing many goods
a Cost decreases as production rates increase
B Average unit cost decreases as more units are produced
C Materials become cheaper when they are purchased in bulk
D Laborers become more productive because of technological advances

10 Rearranging resources so that constant resource levels are maintained is called
a Floating
B Leveling
C Restructuring
D Crashing

11 The _________ is a timephased budget that will be used to measure and monitor cost performance in the project
A Work breakdown structure
b Project schedule
c Cost baseline
d Cost budget

12 To transfer most of the cost risk to the contractor the client may use a ___________ contract
A Cost plus award
b Cost plus incentive fee
c Cost plus fixed fee
d Fixed price

13 An appropriate sequence for risk management activities is
a Risk identification risk quantification and risk response development and control
B Risk identification risk assessment and risk planning
C Risk identification risk mitigation and risk management
D Risk identification risk elimination and risk mitigation

14 Theory X holds that
a Quality improvements lie in the hands of quality circles
B Profits are tied to meeting schedule deadlines
C Absenteeism is tied to poor working conditions
D Workers are inherently unmotivated and need strong guidance


15 All of the following are characteristics of parametric estimating except
a Historical information
B Quantifiable
C Scalable
D Activity lists

16 Inputs to cost budgeting include all of the following except
a Cost baseline
b Cost estimate
c Work breakdown structure
d Project schedule

17 Inputs used during scope planning include all of the following except
a Constraints
B Project charter
C Budgetcost analysis
D Product description

18 Cost control outputs include all of the following except
a Estimate at completion
B Budget updates
C Revised cost estimates
D Cost baseline

19 Risk identification outputs include the following except
a Decision trees
B Inputs to other processes
C Risk symptoms
D Potential risk events

20 Puts into overall change control include all of the following except
a Project plan
B Change requests
C Change control system
D Performance reports

21 Activity duration estimate inputs include all of the following except
a Resource requirements
B Basis of estimates
C Activity lists
D Constraints

22 All of the following are contract types except
a Unitprice
B Makeorbuy
C Cost reimbursable
D Lump sum

23 Initiation inputs for a project include all of the following except
a Product description
B Strategic plan
C Project charter
D Selection criteria

24 Responses to risk threats include all of the following except
a Avoidance
B Acceptance
C Mitigation
D Rejection

25 The process of performance reporting includes all of the following except _____________
A Status reporting
B Progress reporting
C Forecasting
D Product analysis

26 Constrained optimization methods of project selection include
a Scoring models
B Benefitcost ratios
C Multiobjective programming algorithms
D Subjective analyses

27 Which of the following statements concerning contract type is correct
A A fixed price contract contains the most risk for the buyer
B Cost reimbursable contracts offer sellers the highest profit potential
C Lump sum contracts offer sellers the greatest profit potential
D Unit price contracts are illegal in many jurisdictions

28 A Work Breakdown Structure (WBS) numbering system should allow project staff to
a Identify the level at which individual WBS elements are found
B Identify configuration management milestones
C Estimate the costs of WBS elements
D Provide project justification

29 All of the following are true quality statements except
a Quality improvement depends upon better definition and increased awareness of the requirementsspecifications
B Project quality management must address both management of the project and the product of the project
C Recognition of key actions required of each team member is necessary to meet quality objectives
D Computeraided design systems can improve quality but only at the expense of an increase in the cost of design

30 All of the following are examples of tools often used in cost estimating except
a Parametric modeling
B Analogous estimating
C Bottomup estimating
D Activity duration estimates

31 At XYZ Inc the hourly wage for semiskilled workers is 1400 The annual audit shows that fringe benefits cost 30 of basic wages and that overhead costs are 60 of wages plus fringe benefits What is the loaded hourly wage for a semiskilled worker at XYZ Inc
A 2714
B 2896
C 3003
D 2912

32 Of the following estimates which most accurately reflect the actual cost of the project
A Conceptual estimates
B Order of magnitude estimates
C Preliminary estimates
D Bottomup estimates

33 The most crucial time for project risk assessment is
a When a problem surfaces
B During the planning phase
C During the closeout phase
D After the project schedule has been published

34 When there is uncertainty associated with one or more aspects of the project one of the first steps to take is to
a Revise project plan
B Conduct a riskbenefit analysis
C Conduct a needs analysis
D Increase the estimated cost of the project

35 Including a contingency reserve in the project budget is intended to
a Reduce the probability of scope changes
B Increase the probability of scope changes
C Reduce the probability of a cost overrun
D Increase the probability of a cost overrun

36 Given the information in the following table what is the expected value from this risk event
Probability Result
a 10000
B 7500
C + 2500
D 7000

37 A contractor is working on a fixed price contract that calls for a single lump sum payment upon satisfactory completion of the contract About halfway through the contract the contractor project manager informs their contract administrator that financial problems are making it difficult for them to pay their employees and subcontractors The contractor asks for a partial payment for work accomplished Which of the following actions by the buyer is most likely to cause problems for the project
A Starting partial payments for work accomplished
B Making no payments because it would violate the conditions of the contract
C Paying for work accomplished to date
D Negotiating a change to the payment conditions in the contract

38 A precise description of a physical item procedure or service for implementation of an item or service is called :
a Work package
B Baseline
C Product description
D Work breakdown structure (WBS) element

39 A project should be terminated for all of the following reasons except
a Lack of team synergy
B The project no longer meets the company's objectives
C The resources are not available to complete project activities
D Project funding has been significantly reduced

40 One common way to compute estimated at completion (EAC) is to take the project budgetedatcompletion and
a Divide it by the schedule performance index
B Multiply it by the schedule performance index
C Multiply it by the cost performance
D Divide it by the cost performance index


参考答案
1B 2A 3C 4B 5C 6A 7A 8D 9B10B 11C 12D 13A 14D 15D 16A 17C 18D 19A 20C
21B 22B 23C 24D 25D 26C 27C 28A 29D 30D 31D 32D 33B 34B 35C 36D 37B 38C 39A 40D

文档香网(httpswwwxiangdangnet)户传

《香当网》用户分享的内容,不代表《香当网》观点或立场,请自行判断内容的真实性和可靠性!
该内容是文档的文本内容,更好的格式请下载文档

下载文档,方便阅读与编辑

文档的实际排版效果,会与网站的显示效果略有不同!!

需要 2 积分 [ 获取积分 ]

购买文档

相关文档

PMP考试模拟题(20个)

Communications Sample Questions1. Which of the following is not a process of Project Communcations Management? A. Administrative Closure B. Performance Reporting C. Information Distrib

4***2 8年前 上传467   0

PMP考试模拟题(28个)

Sample Professional Responsibility exam questions1.  While working on an external project your customer asks you to perform some additional tasks that are not included in the formal contract. You

h***9 10年前 上传588   0

PMP项目管理模拟考试卷——16-2004.模拟考试试题

1. What are the 4 stages of team development?a. Assignment, kick-of, training, communicatingb. Forming, storming, norming, performing c. Direction, motivation, cooperation, collaboration d.

H***1 10年前 上传550   0

PMP项目管理模拟考试卷——5-科兹纳PMP模拟试卷

概述1、项目是一系列——的活动和任务。A、具有特定目标。B、具有明确开始和终止日期。C、资金有限(如果可用)。D、消耗资源。E、以上皆是。2、成功的项目管理可以被定义为——达到了项目管理目标。A、及时地。B、没有成本超支。C、在设计的性能/技术水平上。D、以上皆是。 E、只有A和B。3、项目管理的好处在于能够——辨别问题,从而产生——。

y***2 12年前 上传961   0

PMP项目管理模拟考试卷——17-成都模拟题

1. To help the project team function more efficiently on complex and interrelated tasks, the project manager decides to use a war room. What does this mean?A. All the project records are kept in ma

y***l 12年前 上传428   0

PMP项目管理模拟考试卷——18-成都模拟题答案

模拟题答案1C21C41D61C81C2C22D42D62B82A3B23D43B63A83A4A24B44D64A84B5A25B45C65C85B6B26A46A

y***i 10年前 上传587   0

PMP项目管理模拟考试卷——9-(IPMP)认证考核试题

国际项目管理专业资质认证(IPMP)知识考核笔试试题 题号分数阅卷人一二三四五六七总分级 别: IPMA C级 考 点:

x***5 10年前 上传632   0

PMP项目管理模拟考试卷——22-IPMA C级试卷

华鼎项目管理论坛 国际项目管理专业资质认证(IPMP) 知识考核笔试试题 级 别: IPMA C级 应试人员: 准考证号: 分 数: 阅 卷 人: IPMA国际项目管理专业资质认证中国认证委员会 试题1:(20分) 黄河机械公司是一家以

绿***踪 12年前 上传681   0

PMP项目管理模拟考试卷——23-IPMA D级试卷

华鼎项目管理论坛 国际项目管理专业资质认证(IPMP) 知识考核笔试试题 级 别: IPMA D级 应试人员: 准考证号: 分 数: 阅 卷 人: IPMA国际项目管理专业资质认证中国认证委员会 一、判断题 (每小题1分,共20分) 1.

d***3 12年前 上传1010   0

PMP考试学习心得

PMP考试学习心得  我几乎都是利用自己的业余时间进行PMP和项目管理学习的,一般都在项目上很忙,时间时非常的宝贵的,我最初就是这样计划的,一定找一家让我省力气的、高效的培训班,这样我投入的精力也会少些,所以在选机构上花了大把时间考察。后来证明,这个过程的确是磨刀不误砍柴工,我筛选了几家培训机构之后,选了智鼎东方。  我把备考PMP就定义成一个项目,用项目管理的办法管理学习,整个备考过程

L***9 12年前 上传417   0

PMP考试的100个关键点

1. 一个项目在启动阶段会进行量级估算,准确范围是-50至100%。2000版的量级估算准确度为:-25%到+75%。 参考:PMBOK2004 P161 CH P137 7.1 成本估算。 2. 质量控制通常先于范围确认执行,但这两个过程可以并列进行参考3. Cost-plus-fixed-fee(CPFF) 成本加固定费用合同。成本补偿型合同包括成本加固定费用(CPFF)、成本加

i***i 12年前 上传456   0

2002年PMP考试的一些信息

          2002年PMP考试的一些信息一、2002年PMP考试日期表考试日期3月23日6月22日9月21日12月7日报名截止日期1月15日4月12日7月12日9月30日提交材料截止日期1月18日4月18日7月18日10月4日退考截止日期2月15日5月13日8月2日10月30日缓考截止日期

z***2 14年前 上传444   0

PMP考试技巧24计

PMP考试技巧24计 第1计 先调查,后决策例1:在新公司,你发现公司的一些财物报告没有遵照会计准则,所以并不准确,在这种情况下,你首先要做的是? A、将公司不准确的记账操作通知政府B、与你的财物经理沟通,告知他你为什么认为他们违反了会计准则C、既然你是公司的新员工,你假设公司的财务标准是不同的,所以不用采取任何行动D、与你以前的财务经理交流,对新公司的会计标准获得专家

j***8 9年前 上传445   0

PMP项目管理模拟考试卷——21-项目管理师模拟试卷

项目管理师模拟试卷1、 单项选择题:(1) 确定项目范围的工具是:(C)A. PROJECT 2000;B. CPM;C. WBS;D. PERT;(2) 在项目管理过程中,自制-外购分析应用于哪种场合?(C)A. 招投标时;B. 合同谈判时;C. 编制项目的采购计划时;D. 寻价时;(3) 如果一个项目涉及众多的职能部门,而且比较复杂,则最好

h***i 12年前 上传667   0

2019编导艺考模拟真题和2018考试真题

2019 编导艺考模拟真题《我们诞生在中国》是一部()A.剧情片B.纪录片C.美术片D.科教片一般标准电影帧数为()A 24B 25C 48D 602016年10月17日7:30分,神舟十一号成功发射。下列哪位航天员三度飞天()A 翟志刚B 刘伯明C 景海鹏D 聂海胜鲍勃·迪伦不具备以下哪个身份?()A 歌手B 作家

l***金 4年前 上传2057   0

2023年教师招聘考试填空题模拟试题及答案(2)

1、 教育心理学是一门研究学校情境中 学与教 的基本心理规律的科学。 2 教育心理学是 应用心理学 的一种,是心理学与教育学的交叉学科。3、 所谓心理发展,是指个体从出生、成熟、衰老直至死亡的整体生命进程中所发生的一系列 心理变化 。 4、 学生心理发展的基本特征是:连续性与阶段性、定向性与顺序性、不平衡性 与差异性。5、 学生性格差异主要是指性格的特征差异和性格的类型差异 。

公***够 4个月前 上传110   0

2023年小学教师招聘考试多项选择题模拟试题及答案

1.教育活动的基本规律包括。A.教育与生产力之间的矛盾或关系B.教育与社会发展之间的矛盾或关系C.教育现象内部各要素之间的矛盾或关系D.教育与人的身心发展之间的矛盾或关系E.教育与生产关系之间的矛盾或关系

陡***鳅 4个月前 上传196   0

2023年司法考试《法理学》不定项选择题模拟试题及答案

 1.依据宪法,下列哪个领导人或机关或组织必须向全国人民代表大会报告工作?  A.中华人民共和国主席  B.中央军委主席  C.全国人大常委会  D.中国人民政治协商会议  答案:C。  2.依据宪法,下列哪些领导人或机关或组织必须向全国人民代表大会负责?( )  A.中华人民共和国主席

反***组 4个月前 上传209   0

2023年小学教师招聘考试多项选择题模拟试题及答案

1.教育活动的基本规律包括。A.教育与生产力之间的矛盾或关系B.教育与社会发展之间的矛盾或关系C.教育现象内部各要素之间的矛盾或关系D.教育与人的身心发展之间的矛盾或关系E.教育与生产关系之间的矛盾或关系2.下列学科从属于教育科学体系的是。A.教育哲学

反***组 4个月前 上传122   0

PMP学习心得

PMP学习心得  我参加的XX年1月的培训班,3月23日考试。成绩不算高但庆幸通过了,回顾整个学习,复习,考试各阶段,把自己的经验教训总结分享给各位同学。  01. 提前报名,课前通读一遍。    坦白说,我是属于笨鸟先飞的类型,12月中旬开始看pmbok,从第五章开始看,依据恒佳提供的打印版复习题为线索,根据问题在pmbok中找答案,把每章的问题都看一遍,在书中找一遍答案,基本pm

姜***8 10年前 上传594   0

pmp学习心得

pmp学习心得第一篇:pmp学习心得pmp考试心得三个月紧张而富挑战的pmp备考结束了, pmp考试也是一个理顺项目管理思路的过程,在知识点,尤其是职业道德的理解上要以pmp思路对待,重要的是理解pmi的概念和思想。同时也将如何进行项目管理的水平又提升到一个新的高度,发现了诸多平时工作中存在的问题,也对今后起到了指导与改正的作用,真正是受益匪浅。1. 学到的知识总结pmbok

w***i 10年前 上传504   0

2019收集中考语文模拟试题(参考试题)

2019收集中考语文模拟试题(参考试题)   一、积累(16分)   1.阅读下面文字,根据语境完成后面的题目。(4分)   歌声如飘风,如一(lǚ) ▲ 摇曳的游丝,在夜空中遥远地传来,渐行渐近,渐渐地清越,终于到了窗下,歌词也清晰可▲了。咿呀的桨声,夹着(jī) ▲ 荡的水声,缓慢地为歌声击节。然后歌声又渐渐远去,渐渐地微弱,渐渐地模糊,终于轻烟般在静夜中消失。   (摘自柯灵《枕畔

y***a 5年前 上传939   0

2021年山东省东营市人教版数学中考试题真题模拟试题含解析答案

1、 16 的算术平方根是 ( ) A . 4 B . -4 C . D . 8 2、 下列运算结果正确的是( )

4***1 3年前 上传514   0

PMP项目管理模拟考试卷——7-程运鹏项目管理练习题

项目管理练习题1. 授权给项目团队要求项目经理提供下列事项,但除了:A. 拥有和归宿感B. 详细的项目计划C. 指挥和领导D. 共同的目标2. 项目经理要花很多时间与项目干系人进行沟通交流,下列哪项方法或技术会对项目经理最有用,以便项目团队齐心协力使项目成功。A. 定期分析工作以决定排除什么事项B. 明确优先事项C. 在精力高峰期,安排最有趣的活动D.

s***n 12年前 上传412   0

PMP道德规范

PMI MEMBER ETHICAL STANDARDSMEMBER CODE OF ETHICS The Project Management Institute (PMI) is a professional organization dedicated to the development and promotion of the field of project ma

y***x 9年前 上传458   0